The Pinnacle

Kilnbridge successfully completed the largest drilling and sawing contract ever undertaken in the UK at the Pinnacle, 38 Bishopsgate. This formed an integral part of the overall demolition and piling contracts.

The piles installed on the Pinnacle are the largest ever placed in the UK at 65m deep. The stalled £1billion development would have been the tallest building in the UK at 63 storey’s high (288m).

The Pinnacle - London

Key Facts

Location:
Bishopsgate, London
Contractor:Keltbray Ltd.
Client:Arab Investments
Value:£2.265m

Kilnbridge completed 2 major packages namely, the formation of circular and octagonal openings in four levels of concrete floor slabs of varying thicknesses from 450mm to 3.40m to facilitate the installation of 2.40m diameter pile foundations from ground level. A total of 8677 l/m was diamond stitch drilled and a total of 708m² was diamond wire sawn on the pile enabling works.

We also completed major concrete cutting of structural beams and columns to facilitate the controlled demolition of the existing structure.

Largest drilling and sawing contract ever undertaken in the UK