The Crossrail Western Route section comprised infrastructure and station enhancements to the existing rail network, undertaken in conjunction with Network Rail. Balfour Beatty Rail appointed Kilnbridge to undertake a key element of the Maidenhead remodelling works – the complete reconstruction of Platform 5 during the 2013 Christmas possession on a full package basis.
The project entailed the complete demolition and removal of 200m of Platform 5 (Bourne Branch) and reconstruction to revised levels and curvature. All Platform works were required to be undertaken during back-to-back 57 hour and 70 hour possessions commencing Christmas Eve 2013, with a partial handback to operator First Great Western 57 hours after commencement which required the station and adjoining platform to return to full operation.
The project required extensive pre-possession planning and ground investigation works by Kilnbridge in close co-operation with BBR and Network Rail. 700m³ of existing brickwork, spoil and obstructions were excavated and removed and replaced with 105 bespoke inverted Tee pre-cast wall units together with new drainage, backfill, copers and surfacing utilising a complex arrangement of road-rail vehicle movements. The project was successfully completed and handed back on time.