Scope of works
Kilnbridge undertook works during Christmas of 2020 to strengthen Camden Bridge superstructure in accordance with Form AA/BA. Strengthening works required elements able to provide a deck capable of supporting RA10 at 20mph, thus allowing for Heavy Axle Weight permissions for the structure.
The Kilnbridge scope included:
- Temporary works jacking scheme
- Lead paint removal (CLAW regulations) surface preparation
- Industrial paint application N1/ M24
- Removal of existing rivets (rivet busting)
- Hour by hour programming
- Possession planning 24hr shifts
- New GRP walkway
- Bridge strengthening to sides of bridge
Challenges / Achievements
- Kilnbridge were heavily involved in the planning stage to reduce the amount of propping required, developing a jacking scheme that consequently saved time and money for J Murphy and Network Rail
- The strengthening works were completed on time, on budget and without any incidents
- J Murphy & Sons and Network Rail considered the project a success, leading to Kilnbridge being appointed again in December 2021 to deliver the next phase of the works